A plan needs review when its assumptions change. Triggers include a new supplier, revised
customer use, an equipment change, repeated complaints, audit findings, or a change in applicable requirements. A scheduled review is useful even when no problem has been reported, because silence does not prove that the plan remains suitable.
Change control is a defined process for evaluating, approving, carrying out, and documenting changes. An impact assessment examines how a proposed change could affect connected activities and outcomes. Replacing a shipping container may influence temperature protection, packing instructions, storage space, supplier checks, and customer information.
A sound change process follows a clear sequence:
1. Describe the proposed change and the reason for it.
2. Identify affected requirements, risks, people, records, and procedures.
3. Determine the evidence, resources, and approvals needed before use.
4. Obtain the required approvals and complete implementation preparations, including necessary training and communication, before the effective date.
5. Implement the approved change, verify completion, assess its effectiveness over a suitable period, address problems, and retain the change history.
The plan should state the effective date and how staff distinguish old from new arrangements. Materials in storage or transit may need separate assessment. For an urgent temporary change, define its controls, authorization, duration, review date, and conditions for ending it. Preserve the applicable records and prior versions. Urgency does not remove the need for a controlled response.
This page titled 4.8: Updating a quality plan when requirements or processes change was last modified on Mon, 02 Nov 2026 07:00:23 GMT and is shared under a CC BY-SA 4.0 license and was authored, remixed, and/or curated by Emalee MacKenzie.