1 .
Which of the following would not be expected for qualification of a wire/plasma DED facility?
Quality management system
Wire feedstock source qualification
Wire/Plasma machine qualification
NDT lab
2 .
Which of the following is out of order for qualification?
Installation qualification
Operational qualification
Part qualification
Factory acceptance testing
3 .
Which is not a feature of operational qualification?
Multiple feedstock lots of the specified material
Encompassing a defined portion of build volume
Multiple machine operators
Multiple coupon orientations
Material properties
4 .
Which is generally the most involved and expensive form of part qualification?
Lot acceptance testing
First article testing
Component testing
Destructive testing
5 .
Which of the following is false?
A given feedstock can be qualified to multiple overlapping specifications
All industries only allow feedstock manufacturing facilities to be qualified
Feedstock qualification often requires analysis of multiple lots
Feedstock qualification can involve a full range of properties beyond chemistry
6 .
Which of the following is not an example of lot acceptance testing?
Checking the chemistry of a witness coupon
Tensile testing in the X and Z directions
Review of build and heat treat data to ensure conformity to specification
Radiographic inspection of every part in the build