Organize how changes to a design in the development and realization stages can be registered and processed in BIM. These changes may refer to:
- Change to a property of a symbol (e.g. lengthening of a wall)
- Change of the type of a symbol (e.g. change of family for a door)
- Change in a relation between symbols (e.g. relocation of a door in a wall)
- Change in a time property of a symbol (e.g. as a result of a scheduling change)
Organize the process of change management in both stages as a series of tasks that reflect the above types of changes and take into account possible causes of change, such as:
- Changes in the brief (e.g. new activities added)
- Changes in the budget (e.g. increase of façade cost necessitating reduction of cost elsewhere)
- Changes in an aspect of the design (e.g. change in the heating solution or the fire rating of internal doors and ensuing interfacing issues – not just clash detection)
- Changes in the construction schedules (e.g. due to delays in the delivery of components or to bad weather)
- Errors in construction (e.g. wrong dimensioning or specifications of an element)
Deliverables
- Process and information diagrams, accompanied by short explanatory comments
- Basic model in a BIM editor demonstrating the way changes can be implemented
- Short overview of findings (two A4 sheets)
Roles
If the exercise is a group assignment, consider roles for the following aspects:
- Process management
- Information management
- BIM modelling
- Case analyses (for finding realistic examples)
This page titled 4.3: Exercise II- change management was last modified on Fri, 05 Mar 2021 08:23:57 GMT and is shared under a CC BY-NC-SA 4.0 license and was authored, remixed, and/or curated by Alexander Koutamanis (TU Delft Open Textbooks) via source content that was edited to the style and standards of the LibreTexts platform.